This project was Certified on March 13, 2013

Sector

Water / Wastewater

Location

San Luis, Arizona, USA

Benefited Population

24,000 people

Projected Cost

$630,000.00 USD

Sponsor

City of San Luis

ID#

779

The Project consists of constructing a new 16-inch diameter and approximately 8,733 linear feet long PVC water transmission line to interconnect two separate water distribution systems on the east side of the city of San Luis, Arizona.

    Certification Document

Close Out Report

Close Out Report

The Close‐Out Process provides a review of physical facilities constructed, facility performance and achievement of objectives, as reflected in a results measurement matrix.

    Close Out Report   (PDF, 334 KB)