This project was Certified on May 04, 2010

Sector

Water / Wastewater

Location

Cd. Juárez, Chihuahua, MEX

Benefited Population

723 people

Projected Cost

$1,310,000.00 USD

Technical Assistance

$5,755.00USD from PDAP

Sponsor

Junta Central de Agua y Saneamiento de Chihuahua

ID#

616

The project consist of the construction of wastewater Collection and Construction of the Wastewater Treatment Plant for Jesus Carranza, Chihuahua.

    Certification Document

Close Out Report

Close Out Report

The Close‐Out Process provides a review of physical facilities constructed, facility performance and achievement of objectives, as reflected in a results measurement matrix.

    Close Out Report   (PDF, 147 KB)