This project was Certified on March 20, 2002

Sector

Water / Wastewater

Location

Eagle Pass, Texas, USA

Benefited Population

45,878 people

Projected Cost

$105,340,000.00 USD

Sponsor

Pueblo Nuevo Corporation

ID#

109

The project proposes a regional approach to the treatment and supply of potable water and the collection and treatment of wastewater, it consists of rehabilitation and expansion of the existing water treatment plant, rehabilitation and expansion of the water distribution system, the expansion of the collection system and a new wastewater treatment plant.

    Certification Document