The project includes a water treatment system known as activated alumina and the construction of a 1,200 linear feet of eight-inch PVC C-900 water line extension connecting the Smith Well to the Water Treatment Plant (WTP). The project also includes the installation of 3,720 linear feet of ten-inch HDPE sewer line to connect to an existing manhole and dispose of backwash flush water.
Close Out Report
Close Out Report
The Close‐Out Process provides a review of physical facilities constructed, facility performance and achievement of objectives, as reflected in a results measurement matrix.