This project was Certified on April 23, 2015

Sector

Water / Wastewater

Location

Sunland Park, New Mexico, USA

Benefited Population

6,438 people

Projected Cost

$11,700,000.00 USD

Sponsor

Camino Real Regional Utility Authority

ID#

738

The existing Sunland Park North WWTP, has failed and is used strictly for pretreatment, the south WWTP is used to complete treatment to complete treatment. The existing North WWTP will be replaced with a new activated sludge plant capable of treating approximately 1.00 MGD of wastewater.