This project was Certified on June 18, 1997

Sector

Water / Wastewater

Location

Tijuana, Baja California, MEX

Benefited Population

1,540,072 people

Projected Cost

$27,430,000.00 USD

Sponsor

Comisión Estatal de Servicios Públicos de Tijuana

ID#

100

This Project includes the construction of a new parallel system for the conveyance of wastewater from its concentration point at the border with the United States for treatment at the San Antonio de los Buenos Wastewater Treatment Plant, and the expansion and rehabilitation of the San Antonio de los Buenos wastewater treatment plant.

    Certification Document

Close Out Report

Close Out Report

The Close‐Out Process provides a review of physical facilities constructed, facility performance and achievement of objectives, as reflected in a results measurement matrix.